Discussion about this post

User's avatar
Delivery Dates Research's avatar

Hi Nick, Chris and Steven,

I write Delivery Dates Research. We take the delivery and energization dates that data-center operators and miners file with the SEC and check them against what their later filings say. Basically, it's a receipt drawer for the build-out.

Your Oct 23 queue update tracking a new fast-track for load in MISO is the large-load side of the same story we follow from the filings end.

I've added Interconnection.fyi to our recommendations because it fits our readers. If ours fits yours, a recommendation back would be great, but there's no obligation. Either way, I'll keep reading.

Delivery Dates Research

hello@deliverydatesresearch.com

Forced Futures's avatar

PJM's Expedited Interconnection Track got 2.1 GW from its first three projects. How will you judge whether EIT is actually faster: time to a signed GIA, or time to in-service? Those two BPA records still listing 2018 and 2021 in-service dates make me trust only the second.

1 more comment...

No posts

Ready for more?