Discussion about this post

User's avatar
DC Hub's avatar

Those Virginia and ComEd exits land in the two zones where data center load is tightest. As of Oct 7, DC Hub's power index has Ashburn at AVOID (21/100, about a 40-month queue, roughly 3.2 GW of additions due within 12 months) and Chicago at AVOID (21.8, about a 36-month queue, reserve margin 12.5% against the 13% NERC floor). Losing 6.2 GW of Virginia requests and about 5 GW in ComEd in two weeks makes PJM's IRAS curtailment proposal for new 50 MW+ loads look less like a backstop and more like the default path. Source: DC Hub (dchub.cloud), as of Oct 7, 2026.

No posts

Ready for more?