๐ Interconnection Weekly: Project Updates You Need to Know (12/23/2024 - 12/30/2024)
5 projects moved in the interconnection queues across the country in the past week
This week, we saw the following updates to U.S. transmission grid interconnection projects. For access to our live dataset, contact our sales team here.
Huntington Jct. 138 kV โ 150MW battery + solar ๐โ๏ธ project in Huntington County, IN (PJM). Proposed completion changed from May 31, 2022 to December 30, 2026
Aster 138kV Substation โ 100MW solar โ๏ธ project in Perry County, IL (MISO). Proposed completion changed from August 31, 2023 to December 30, 2026
Cartersville Solar โ 99MW solar โ๏ธ project in Powhatan County, VA (PJM). Proposed completion changed from March 14, 2024 to May 16, 2026
Rippon โ 99MW solar โ๏ธ project in Jefferson County, WV (PJM). Proposed completion changed from December 30, 2025 to December 30, 2026
Twin Groves Storage II, Blue Mound 345 kV โ 50MW battery ๐ project in Mclean County, IL (PJM). Proposed completion changed from October 30, 2023 to January 27, 2028





