This week, we saw the following updates to U.S. transmission grid interconnection projects. For access to our live dataset, contact our sales team here.
Huntington Jct. 138 kV โ 150MW battery + solar ๐โ๏ธ project in Huntington County, IN (PJM). Proposed completion changed from May 31, 2022 to December 30, 2026
Aster 138kV Substation โ 100MW solar โ๏ธ project in Perry County, IL (MISO). Proposed completion changed from August 31, 2023 to December 30, 2026
Cartersville Solar โ 99MW solar โ๏ธ project in Powhatan County, VA (PJM). Proposed completion changed from March 14, 2024 to May 16, 2026
Rippon โ 99MW solar โ๏ธ project in Jefferson County, WV (PJM). Proposed completion changed from December 30, 2025 to December 30, 2026
Twin Groves Storage II, Blue Mound 345 kV โ 50MW battery ๐ project in Mclean County, IL (PJM). Proposed completion changed from October 30, 2023 to January 27, 2028





