This week, we saw the following updates to U.S. transmission grid interconnection projects. For access to our live dataset, contact our sales team here.
GREC #2 Interconnect Substation β 345kV β 582MW battery + gas ππ₯ project in Chouteau County, OK (SPP). Proposed completion changed from May 31, 2027 to September 30, 2026
Aspen Road Solar β 100MW solar βοΈ project in Franklin County, PA (PJM). Proposed completion changed from March 7, 2026 to March 7, 2025
Flatrock Creek Solar II β 100MW solar βοΈ project in Allen County, IN (PJM). Proposed completion changed from October 30, 2024 to December 30, 2028
Flatrock Creek Storage I β 50MW battery π project in Allen County, IN (PJM). Proposed completion changed from October 30, 2024 to December 30, 2028
Scioty Solar, South Kenton 138 kV β 49MW solar βοΈ project in Hardin County, OH (PJM). Proposed completion changed from October 30, 2023 to September 30, 2027
LASSEN LODGE HYDROELECTRIC β 4MW hydro π§ project in Tehama, CA (CAISO). Proposed completion changed from October 15, 2024 to October 14, 2027
Battery Storage β 289MW battery π project in New London County, CT (ISO-NE). Proposed completion changed from September 30, 2024 to September 30, 2027
Battery Storage β 262MW battery π project in New Haven County, CT (ISO-NE). Proposed completion changed from September 30, 2024 to September 30, 2027
Battery Storage β 136MW battery π project in New Haven County, CT (ISO-NE). Proposed completion changed from September 30, 2024 to September 30, 2027
Jones St. No 1201 69kV substation β 11MW battery π project in Douglas County, NE (SPP). Proposed completion changed from May 30, 2026 to February 27, 2027