This week, we saw the following updates to U.S. transmission grid interconnection projects. For access to our live dataset, contact our sales team here.
La Pine - Chiloquin No 1 line. β 1000MW battery + solar πβοΈ project in Klamath County, OR (West). Proposed completion changed from November 30, 2023 to December 31, 2026
Axis Ridge Wind β 750MW wind π¨ project in Sutton, TX (ERCOT). Proposed completion changed from June 30, 2030 to January 30, 2029
Pinnington Storage β 508MW battery π project in Jack, TX (ERCOT). Proposed completion changed from October 14, 2025 to April 29, 2026
Tehuacana Creek Solar SLF β 505MW solar βοΈ project in Navarro, TX (ERCOT). IA date added November 24, 2024
BRP Artemis BESS β 411MW battery π project in Grimes, TX (ERCOT). Proposed completion changed from May 31, 2025 to November 30, 2028
HyFuels Green Lake Solar β 346MW solar βοΈ project in Victoria, TX (ERCOT). Proposed completion changed from September 30, 2026 to November 30, 2027
Three Canes Solar SLF β 333MW solar βοΈ project in Navarro, TX (ERCOT). IA date added November 26, 2024
Quantum Storage β 321MW battery π project in Haskell, TX (ERCOT). IA date added October 25, 2023
Tyler BESS β 305MW battery π project in Smith, TX (ERCOT). Proposed completion changed from September 20, 2026 to June 29, 2027
Yellow Cat Wind β 301MW wind π¨ project in Navarro, TX (ERCOT). Proposed completion changed from March 30, 2026 to September 29, 2026
PP Jaguar Solar β 300MW solar βοΈ project in Mclennan, TX (ERCOT). Proposed completion changed from May 31, 2026 to February 10, 2027
Inadale BESS β 286MW battery π project in Scurry, TX (ERCOT). Proposed completion changed from December 14, 2026 to July 28, 2027
Inadale Solar β 281MW solar βοΈ project in Scurry, TX (ERCOT). Proposed completion changed from December 14, 2026 to July 28, 2027
Sentinel Solar β 271MW solar βοΈ project in La Salle, TX (ERCOT). Proposed completion changed from December 22, 2027 to January 23, 2029
Santa Garcias Solar β 265MW solar βοΈ project in Kleberg, TX (ERCOT). Proposed completion changed from May 30, 2026 to January 31, 2029
Mystic Springs Renewable Energy Solar SLF β 258MW solar βοΈ project in Kaufman, TX (ERCOT). Proposed completion changed from September 13, 2026 to August 30, 2027
Bell County Morgan Storage β 256MW battery π project in Bell, TX (ERCOT). Proposed completion changed from September 30, 2026 to March 31, 2028
Nautilus Heavy Storage β 256MW battery π project in San Patricio, TX (ERCOT). Proposed completion changed from May 29, 2026 to December 30, 2027
HyFuels Western Farmland Wind β 253MW wind π¨ project in Victoria, TX (ERCOT). Proposed completion changed from April 1, 2026 to June 29, 2027
Adamstown Solar β 251MW solar βοΈ project in Wichita, TX (ERCOT). Proposed completion changed from September 29, 2026 to August 30, 2027
August Draw Energy β 250MW solar βοΈ project in Reeves, TX (ERCOT). Proposed completion changed from July 30, 2027 to June 26, 2028
Taylor Creek, Marysville-Gunn Road 345 kV β 250MW solar βοΈ project in Hardin County, OH (PJM). Proposed completion changed from December 3, 2023 to March 30, 2028
Coyote Wind β 242MW wind π¨ project in Scurry, TX (ERCOT). Proposed completion changed from June 30, 2024 to January 30, 2025
Cumulus Grid BESS β 210MW battery π project in Ellis, TX (ERCOT). Proposed completion changed from May 31, 2027 to December 31, 2027
SOHO BESS β 206MW battery π project in Brazoria, TX (ERCOT). Proposed completion changed from June 27, 2025 to August 3, 2026
Hamlet Solar β 204MW solar βοΈ project in Frio, TX (ERCOT). Proposed completion changed from August 31, 2027 to September 4, 2028
Hamlet Storage β 204MW battery π project in Frio, TX (ERCOT). Proposed completion changed from August 31, 2027 to September 4, 2028
Ceres BESS β 202MW battery π project in Hunt, TX (ERCOT). Proposed completion changed from December 30, 2026 to November 29, 2027
Elbus BESS, BRP Elbus BESS β 200MW battery π project in Caldwell, TX (ERCOT). Proposed completion changed from November 30, 2026 to November 30, 2027
APV Plumwood Storage β 200MW battery π project in Chambers, TX (ERCOT). IA date added September 2, 2024
DESERT JEWEL STORAGE β 200MW battery π project in San Diego, CA (CAISO). Proposed completion changed from October 29, 2025 to February 4, 2029
Cascabel Wind 2 β 197MW wind π¨ project in Zapata, TX (ERCOT). Proposed completion changed from November 30, 2026 to November 30, 2027
Camino Santiago Solar β 196MW solar βοΈ project in Milam, TX (ERCOT). IA date added December 5, 2024
Corralitos Wind 1 β 196MW wind π¨ project in Zapata, TX (ERCOT). Proposed completion changed from November 30, 2026 to November 30, 2027
Corralitos Wind 2 β 195MW wind π¨ project in Zapata, TX (ERCOT). Proposed completion changed from December 30, 2024 to December 30, 2027
Basketflower Solar β 183MW solar βοΈ project in Eastland, TX (ERCOT). Proposed completion changed from December 30, 2026 to December 30, 2027
Hofbrau BESS β 180MW battery π project in Tom Green, TX (ERCOT). Proposed completion changed from May 4, 2026 to June 30, 2028
Sculpin Solar, Varner - Sowers 138 kV β 180MW solar βοΈ project in Dekalb County, IN (PJM). Proposed completion changed from May 31, 2023 to November 29, 2027
Saddle Horn Station BESS SLF β 177MW battery π project in Comanche, TX (ERCOT). Proposed completion changed from May 31, 2027 to April 9, 2028
Saddle Horn Station Solar SLF β 174MW solar βοΈ project in Comanche, TX (ERCOT). Proposed completion changed from May 31, 2027 to April 9, 2028
Sullivan Solar β 171MW solar βοΈ project in Hidalgo, TX (ERCOT). Proposed completion changed from December 30, 2027 to February 24, 2029
Houston IV BESS β 168MW battery π project in Harris, TX (ERCOT). IA date added November 6, 2024
Fagus Solar Park 1 SLF β 166MW solar βοΈ project in Childress, TX (ERCOT). Proposed completion changed from May 14, 2025 to February 10, 2026
Albatross BESS 2 β 159MW battery π project in Mclennan, TX (ERCOT). Proposed completion changed from August 29, 2025 to February 21, 2028
Cartwheel BESS 2 β 156MW battery π project in Hopkins, TX (ERCOT). Proposed completion changed from June 14, 2025 to June 14, 2026
Antonio Road BESS β 155MW battery π project in Bastrop, TX (ERCOT). Proposed completion changed from May 11, 2026 to May 31, 2027
Eighteenmile Solar SLF β 153MW solar βοΈ project in Goliad, TX (ERCOT). Proposed completion changed from September 1, 2025 to November 30, 2026
Rigel Storage β 151MW battery π project in Ellis, TX (ERCOT). Proposed completion changed from June 30, 2027 to October 29, 2028
Rigel Solar β 151MW solar βοΈ project in Ellis, TX (ERCOT). Proposed completion changed from June 30, 2027 to October 29, 2028
Padua Grid BESS Unit 2 β 150MW battery π project in Bexar, TX (ERCOT). Proposed completion changed from December 31, 2025 to August 30, 2026
Stewart Grady BESS β 150MW battery π project in Martin, TX (ERCOT). Proposed completion changed from September 14, 2026 to August 14, 2027
CH Solterra LLC β 143MW solar βοΈ project in Hopkins, TX (ERCOT). Proposed completion changed from September 16, 2025 to September 29, 2026
Demeter Storage 2 β 138MW battery π project in Caldwell, TX (ERCOT). Proposed completion changed from March 27, 2026 to December 30, 2026
Northington Solar β 129MW solar βοΈ project in Wharton, TX (ERCOT). Proposed completion changed from November 30, 2026 to July 14, 2027
Star Dairy Solar β 125MW solar βοΈ project in Lamar, TX (ERCOT). IA date added December 8, 2024
Nymphaea Solar β 120MW solar βοΈ project in Wichita, TX (ERCOT). Proposed completion changed from December 20, 2025 to June 29, 2027
Harlingen III BESS β 110MW battery π project in Cameron, TX (ERCOT). Proposed completion changed from August 14, 2026 to June 30, 2027
Big River Solar β 104MW solar βοΈ project in Zapata, TX (ERCOT). Proposed completion changed from December 30, 2026 to December 30, 2028
Big Five Storage β 102MW battery π project in Hidalgo, TX (ERCOT). Proposed completion changed from December 29, 2025 to June 29, 2026
Remy Jade III Power Station β 102MW gas π₯ project in Harris, TX (ERCOT). Proposed completion changed from December 5, 2025 to January 15, 2027
Kennedy Solar β 101MW solar βοΈ project in Navarro, TX (ERCOT). Proposed completion changed from November 9, 2025 to December 30, 2028
Matagorda Solar β 101MW solar βοΈ project in Matagorda, TX (ERCOT). Proposed completion changed from December 26, 2025 to August 23, 2026
Myers Solar β 100MW solar βοΈ project in Bee, TX (ERCOT). Proposed completion changed from August 31, 2026 to June 30, 2028
Big Elm Storage β 100MW battery π project in Bell, TX (ERCOT). Proposed completion changed from November 9, 2025 to August 14, 2026
Hana Springs BESS β 100MW battery π project in Lampasas, TX (ERCOT). Proposed completion changed from May 30, 2025 to December 14, 2027
Rutile BESS β 100MW battery π project in Runnels, TX (ERCOT). Proposed completion changed from December 30, 2025 to March 30, 2028
BRP Diran BESS β 100MW battery π project in Wharton, TX (ERCOT). Proposed completion changed from December 31, 2028 to January 30, 2028
GALVANIC BESS β 100MW battery π project in Kinney, TX (ERCOT). Proposed completion changed from November 29, 2025 to December 29, 2026
Blue Summit Energy Storage β 100MW battery π project in Wilbarger, TX (ERCOT). IA date added February 21, 2012
Velado Solar β 96MW solar βοΈ project in Dimmit, TX (ERCOT). Proposed completion changed from September 14, 2027 to September 13, 2028
Velado Storage β 96MW battery π project in Dimmit, TX (ERCOT). Proposed completion changed from September 14, 2027 to September 13, 2028
Basketflower Storage β 92MW battery π project in Eastland, TX (ERCOT). Proposed completion changed from December 30, 2026 to December 30, 2027
The Distribution Providerβs La Fresa - Torrance 66 kV line β 87MW battery π project in Los Angeles, CA (CAISO). Proposed completion changed from August 29, 2024 to November 30, 2028
HappyDogSolar β 85MW solar βοΈ project in Milam, TX (ERCOT). IA date added December 15, 2024
SERENGETI SOLAR β 76MW solar βοΈ project in Delta, TX (ERCOT). Proposed completion changed from September 13, 2026 to September 12, 2027
Myers Storage β 75MW battery π project in Bee, TX (ERCOT). Proposed completion changed from August 31, 2026 to June 30, 2028
Sullivan BESS β 72MW battery π project in Hidalgo, TX (ERCOT). Proposed completion changed from December 30, 2027 to February 24, 2029
Hamby Solar β 71MW solar βοΈ project in Jones, TX (ERCOT). Proposed completion changed from May 29, 2026 to June 26, 2028
Starling Storage β 63MW battery π project in Gonzales, TX (ERCOT). IA date added August 2, 2023
Nymphaea Storage β 61MW battery π project in Wichita, TX (ERCOT). Proposed completion changed from December 20, 2025 to June 29, 2027
Happy Dog Storage β 60MW battery π project in Milam, TX (ERCOT). IA date added December 15, 2024
Albatross BESS β 50MW battery π project in Mclennan, TX (ERCOT). Proposed completion changed from August 29, 2025 to February 21, 2028
Pamplona Solar β 42MW solar βοΈ project in Austin, TX (ERCOT). Proposed completion changed from October 25, 2027 to October 16, 2028
La Mancha Solar β 40MW solar βοΈ project in Zavala, TX (ERCOT). Proposed completion changed from October 7, 2027 to October 9, 2028
La Mancha Storage β 40MW battery π project in Zavala, TX (ERCOT). Proposed completion changed from October 7, 2027 to October 9, 2028
Kennedy Storage β 25MW battery π project in Navarro, TX (ERCOT). Proposed completion changed from November 9, 2025 to December 30, 2028
Hovey Energy Storage β 23MW battery π project in Pecos, TX (ERCOT). Proposed completion changed from December 30, 2025 to December 30, 2026
MULQUEENEY RANCH WIND β 20MW wind π¨ project in Alameda, CA (CAISO). Proposed completion changed from November 29, 2024 to May 31, 2026
Confer Solar I β 20MW solar βοΈ project in Centre County, PA (PJM). Proposed completion changed from June 29, 2025 to May 29, 2026
UN-Kylertown β 20MW solar βοΈ project in Westmoreland County, PA (PJM). Proposed completion changed from September 29, 2021 to October 15, 2025
Boyles Run Solar, Sunbury-Dalmatia 69 kV β 15MW solar βοΈ project in Northumberland County, PA (PJM). Proposed completion changed from July 31, 2022 to April 29, 2027
Boyles Run Solar, Sunbury-Dalmatia 69 kV β 15MW solar βοΈ project in Northumberland County, PA (PJM). Proposed completion changed from July 31, 2023 to April 29, 2027
Cedar Lane Solar β 4MW solar βοΈ project in Queen Annes County, MD (PJM). Proposed completion changed from February 29, 2024 to March 31, 2026
Eighteenmile Storage SLF β battery π project in Goliad, TX (ERCOT). Proposed completion changed from September 1, 2025 to November 30, 2026
Mystic Springs Renewable Energy Storage SLF β battery π project in Kaufman, TX (ERCOT). Proposed completion changed from September 13, 2026 to August 30, 2027
Tehuacana Creek BESS SLF β battery π project in Navarro, TX (ERCOT). IA date added November 24, 2024