π Interconnection Weekly: Project Updates You Need to Know (3/17/2025 - 3/30/2025)
27 projects moved in the interconnection queues across the country in the past 2 weeks
Special Note: Looking to buy or sell a project in the interconnection queue? Weβre actively connecting developers with vetted, transaction-ready buyers and sellers at key decision points. Fill out this short form to get matched with serious players already in the market.
We saw the following updates to U.S. transmission grid interconnection projects. For access to our live dataset, contact our sales team here.
New switching station near Rancho Seco 230 kV Substation β 550MW battery + solar πβοΈ project in Sacramento County, CA (Sacramento Municipal Utility District). Proposed completion changed from December 28, 2028 to December 30, 2029
Burns 345kV Substation β 360MW wind π¨ project in Butler County, KS (SPP). Proposed completion changed from February 28, 2027 to January 30, 2029
Nashua 161 kV Substation β 300MW battery π project in Clay County, MO (SPP). Proposed completion changed from December 30, 2027 to April 30, 2030
Tap of Mingo - Red Willow 345 kV Line β 270MW solar βοΈ project in Decatur County, KS (SPP). Proposed completion changed from December 30, 2025 to December 30, 2028
Q3 new switching station near Cordova 230kV Substation β 250MW battery + solar πβοΈ project in Sacramento County, CA (Sacramento Municipal Utility District). Proposed completion changed from December 30, 2027 to December 30, 2028
New switching station near Hedge 230 kV Substation β 250MW battery π project in Sacramento County, CA (Sacramento Municipal Utility District). Proposed completion changed from September 30, 2027 to September 30, 2028
Bison 345kV Substation β 200MW solar βοΈ project in Johnston County, OK (SPP). Proposed completion changed from November 30, 2024 to November 30, 2027
Wilkes 345 kV Substation β 150MW battery + solar πβοΈ project in Marion County, TX (SPP). Proposed completion changed from September 29, 2026 to March 31, 2027
McCartney 161 kV Substation β 145MW gas π₯ project in Greene County, MO (SPP). Proposed completion changed from December 31, 2025 to December 31, 2026
Magley Solar Energy Center β 135MW solar βοΈ project in Adams County, IN (PJM). Proposed completion changed from December 30, 2024 to March 30, 2029
Brown - South Coleman Junction 138kV line β 113MW solar βοΈ project in Bryan County, OK (SPP). Proposed completion changed from February 1, 2026 to May 31, 2028
Greenwood Solar β 100MW solar βοΈ project in Culpeper County, VA (PJM). Proposed completion changed from December 14, 2025 to October 14, 2026
Dulles Solar β 100MW solar βοΈ project in Loudoun County, VA (PJM). Proposed completion changed from December 30, 2023 to October 30, 2026
Canadian Switch 138 kV Substation β 100MW battery π project in Cleveland County, OK (SPP). Proposed completion changed from December 30, 2026 to December 30, 2027
Silver City 138 kV Substation β 100MW battery π project in Creek County, OK (SPP). Proposed completion changed from December 30, 2026 to December 30, 2027
Talawanda to Canadian River 138 kV Line Tap β 90MW solar βοΈ project in Pittsburg County, OK (SPP). Proposed completion changed from February 1, 2026 to May 31, 2028
Sumac Solar β 80MW solar βοΈ project in Bertie County, NC (PJM). Proposed completion changed from December 30, 2026 to June 30, 2028
Strinestown Solar Project β 79MW solar βοΈ project in York County, PA (PJM). Proposed completion changed from December 30, 2024 to January 6, 2027
Dover Solar β 55MW solar βοΈ project in York County, PA (PJM). Proposed completion changed from October 31, 2024 to October 13, 2026
Prairie Refuge Solar, Kenzie Creek-Stone Lake 69 kV β 50MW solar βοΈ project in Cass County, MI (PJM). Proposed completion changed from October 30, 2023 to May 30, 2028
Concho Solar I β 49MW solar βοΈ project in Queen Annes County, MD (PJM). Proposed completion changed from June 2, 2027 to June 2, 2024
Scioto Solar β 30MW solar βοΈ project in Hardin County, OH (PJM). Proposed completion changed from December 30, 2028 to December 27, 2026
Harrowgate 1 β 20MW solar βοΈ project in Chesterfield County, VA (PJM). Proposed completion changed from March 29, 2025 to June 29, 2027
Dover Solar β 20MW solar βοΈ project in York County, PA (PJM). Proposed completion changed from October 31, 2024 to October 13, 2026
Chester Solar Technology Park β 20MW solar βοΈ project in Chesterfield County, VA (PJM). Proposed completion changed from October 30, 2022 to June 29, 2027
Concho Solar I β 17MW solar βοΈ project in Queen Annes County, MD (PJM). Proposed completion changed from June 2, 2027 to June 2, 2024
Siouxland 69kV β 15MW gas π₯ project in Woodbury County, IA (SPP). Proposed completion changed from February 15, 2023 to February 28, 2022