This week, we saw the following updates to U.S. transmission grid interconnection projects. For access to our live dataset, contact our sales team here.
Four Corners 345kV β 1500MW wind π¨ project in San Juan, NM (Arizona Public Service). Project status changed from Active In Queue to Withdrawn
Queensboro Renewable Express Circuit A β 1310MW wind π¨ project in Queens County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Juno Power Express β 1200MW project in Suffolk County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Four Corners 345kV β 1000MW wind π¨ project in San Juan, NM (Arizona Public Service). Project status changed from Active In Queue to Withdrawn
Four Corners 345kV β 1000MW wind π¨ project in San Juan, NM (Arizona Public Service). Project status changed from Active In Queue to Withdrawn
Vineyard Northeast β 884MW wind π¨ project in Nassau County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Swiftsure Energy Storage β 650MW battery π project in Richmond County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Battery Storage β 528MW battery π project in Bristol County, MA (ISO-NE). Project status changed from Active In Queue to Withdrawn
Cholla 500kV, Delaney 500kV Substation (Q276 POI500kV) β 500MW battery + solar πβοΈ project in Navajo, AZ (Arizona Public Service). Project status changed from Active In Queue to Withdrawn
Proposed Cedar Spring Substation @ 500 kV β 500MW wind π¨ project in Gilliam County, OR (Portland General Electric). Proposed completion changed from May 31, 2019 to January 1, 2015
Cholla 500kV, Delaney 500kV Substation (Q276 POI500kV) β 500MW battery + solar πβοΈ project in Navajo, AZ (Arizona Public Service). Proposed completion changed from May 23, 2021 to December 19, 2024
APS Chevelon 345 kV Substation β 477MW battery π project in Coconino, AZ (Arizona Public Service). Project status changed from Active In Queue to Withdrawn
Proposed Mikkalo Substation @ 500 kV β 400MW wind π¨ project in Sherman County, OR (Portland General Electric). Proposed completion changed from May 31, 2019 to November 30, 2014
Proposed Coyote Springs South Substation @ 500 kV β 400MW wind π¨ project in Umatilla County, OR (Portland General Electric). Proposed completion changed from May 31, 2019 to November 30, 2014
Ridge View Solar Energy Center β 350MW solar βοΈ project in Niagara County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Robinson Grid β 300MW battery π project in Kings County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Battery Storage β 300MW battery π project in Windham County, CT (ISO-NE). Project status changed from Active In Queue to Withdrawn
North Country Wind β 298MW wind π¨ project in Franklin County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Brandon Shores 230 kV β 275MW battery π project in Anne Arundel County, MD (PJM). Project status changed from Active In Queue to Withdrawn
Holbrook Energy Storage II β 260MW battery π project in Suffolk County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Genesee Road Solar Energy Center β 250MW solar βοΈ project in Erie County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Thomas Hill 345 kV, Thomas Hill - McCredie 345 kV β 245MW solar βοΈ project in Randolph, MO (Associated Electric Cooperative, Incorporated). Proposed completion changed from November 14, 2025 to February 14, 2029
Cavalier β 240MW solar βοΈ project in Isle Of Wight County, VA (PJM). Project status changed from Active In Queue to Operational
Primary: Proposed new 115 kV substation between Tono, Blumaer, and Rochester substations β 218MW gas π₯ project in Lewis County, WA (Puget Sound Energy). Project status changed from Active In Queue to Suspended
Alternate: Proposed new 115 kV substation along - South Bremerton β Bremerton 115 kV β 218MW gas π₯ project in Kitsap County, WA (Puget Sound Energy). Project status changed from Active In Queue to Suspended
Blue Frost Solar β 200MW solar βοΈ project in Montgomery County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Sweet Valley Storage β 200MW battery π project in Genesee County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Blue Frost Storage I β 200MW battery π project in Montgomery County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Blue Frost Storage II β 200MW battery π project in Montgomery County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Groveland 115kV Substation β 200MW battery π project in Washington County, OR (Portland General Electric). Project status changed from Active In Queue to Withdrawn
Monitor 115kV Substation β 200MW battery π project in Marion County, OR (Portland General Electric). Project status changed from Active In Queue to Withdrawn
Waconda 115kV Substation β 200MW battery π project in Marion County, OR (Portland General Electric). Project status changed from Active In Queue to Withdrawn
Gresham Substation β 200MW battery π project in Multnomah County, OR (Portland General Electric). Proposed completion changed from December 31, 2023 to August 3, 2028
A new location on/near Warm Springs Reservation β 200MW wind π¨ project in Wasco County, OR (Portland General Electric). Proposed completion changed from May 31, 2015 to May 31, 2013
Proposed Cedar Spring Substation @ 500 kV β 200MW wind π¨ project in Gilliam County, OR (Portland General Electric). Proposed completion changed from May 31, 2019 to September 30, 2015
Proposed Cedar Spring Substation @ 500 kV β 200MW wind π¨ project in Gilliam County, OR (Portland General Electric). Proposed completion changed from May 31, 2019 to September 30, 2015
Casper substation β 199MW solar βοΈ project in Natrona, WY (PacifiCorp). Project status changed from Active In Queue to Withdrawn
Niagara Dolomite Solar β 180MW solar βοΈ project in Niagara County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Morris Ridge Solar Energy Center β 177MW solar βοΈ project in Steuben County, NY (NYISO). Project status changed from Active In Queue to Operational
Erie-Wyoming County Solar β 175MW battery + solar πβοΈ project in Wyoming County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Port Jefferson Energy Storage β 168MW battery π project in Suffolk County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Battery Storage β 167MW battery π project in New London County, CT (ISO-NE). Project status changed from Active In Queue to Withdrawn
Cedar Mountain - Moenkopi 500 kV Line β 161MW wind π¨ project in Coconino, AZ (Arizona Public Service). Project status changed from Active In Queue to Operational
500 kV Moenkopi-Cedar Mountain line β 161MW solar + wind βοΈπ¨ project in Coconino, AZ (Arizona Public Service). Project status changed from Active In Queue to Operational
Yellow Barn Solar β 160MW solar βοΈ project in Tompkins County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Sitgreaves substation β 160MW project in Navajo, AZ (Arizona Public Service). Project status changed from Active In Queue to Withdrawn
CUERNO GRANDE WIND β 150MW wind π¨ project in San Bernardino, CA (CAISO). Project status changed from Active In Queue to Withdrawn
Midway 345 kV II β 150MW solar βοΈ project in Henry County, OH (PJM). Project status changed from Active In Queue to Withdrawn
Dime Energy Storage β 150MW battery π project in Erie County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Wild Grains Solar, Maddox Creek 345 kV β 150MW solar βοΈ project in Van Wert County, OH (PJM). Proposed completion changed from December 30, 2023 to December 30, 2027
Stark Solar β 150MW solar βοΈ project in Stark County, OH (PJM). Proposed completion changed from March 30, 2024 to December 30, 2028
NY115 - Newport Solar β 130MW solar βοΈ project in Oneida County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Wild Ox Solar β 130MW battery + solar πβοΈ project in Yates County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Gravel Road Solar β 128MW solar βοΈ project in Seneca County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
East Setauket Storage β 125MW battery π project in Suffolk County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Battery Storage β 125MW battery π project in Hartford County, CT (ISO-NE). Project status changed from Active In Queue to Withdrawn
Barkley - Caldwell 161kV Line β 125MW solar βοΈ project in Lyon County, KY (MISO). Project status changed from Active In Queue to Withdrawn
Starwood 115 kV β 125MW battery π project in King County, WA (Puget Sound Energy). Project status changed from Active In Queue to Suspended
Sapphire Sun β 120MW solar βοΈ project in Allegany, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Pine Hill Storage β 120MW battery π project in Chautauqua County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Jackson Generation β 120MW gas π₯ project in Will County, IL (PJM). Proposed completion changed from April 25, 2024 to December 31, 2026
Union Energy Center, LLC β 116MW battery π project in Putnam County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Wagner 115 kV β 115MW battery π project in Anne Arundel County, MD (PJM). Project status changed from Active In Queue to Withdrawn
Margarita Storage β 110MW battery π project in Ulster County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Cascade - Rocky Reach 230kV Line β 100MW solar βοΈ project in Douglas County, WA (Puget Sound Energy). Project status changed from Active In Queue to Suspended
Cascade - Rocky Reach 230kV Line β 100MW solar βοΈ project in Douglas County, WA (Puget Sound Energy). Project status changed from Active In Queue to Suspended
Robbins 138 kV β 100MW solar βοΈ project in Westmoreland County, PA (PJM). Project status changed from Active In Queue to Withdrawn
Deer River Wind β 100MW wind π¨ project in Lewis County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Catskill Grid, LLC β 100MW battery π project in Greene County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Fort Edward Solar Farm (NY53) β 100MW solar βοΈ project in Washington County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Westtown Energy Storage β 100MW battery π project in Orange County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Dix Hills Storage, LLC β 100MW battery π project in Suffolk County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Sweet Valley Solar β 100MW solar βοΈ project in Genesee County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
File Cabinet Storage β 100MW battery π project in Ulster County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Warrior Storage β 100MW battery π project in Erie County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
North Seneca β 90MW solar βοΈ project in Seneca County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Yellow Feather β 90MW solar βοΈ project in Fulton County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Fork Union 230 kV β 85MW solar βοΈ project in Fluvanna County, VA (PJM). Project status changed from Active In Queue to Withdrawn
Frederickson 115 kV Substation β 85MW battery π project in Pierce County, WA (Puget Sound Energy). Project status changed from Active In Queue to Suspended
Clubhouse-Lakeview 230 kV β 80MW solar βοΈ project in Greensville County, VA (PJM). Project status changed from Active In Queue to Withdrawn
Clubhouse - Jarratt 115 kV β 80MW battery + solar πβοΈ project in Greensville County, VA (PJM). Project status changed from Active In Queue to Withdrawn
Tabletop Solar β 80MW solar βοΈ project in Montgomery County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
KCE NY 19 β 80MW battery π project in Orange County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
South Suffolk Storage β 77MW battery π project in Suffolk County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Holmes Creek-Highlands City 230kV β 75MW battery + solar πβοΈ project in Jackson, FL (Florida Power & Light). Proposed completion changed from February 28, 2026 to February 28, 2029
Deerhaven (GVL)-Bradford 138kV β 74MW battery + solar πβοΈ project in Bradford, FL (Florida Power & Light). Proposed completion changed from August 31, 2026 to June 24, 2027
Deerhaven (GVL)-Bradford 138kV β 74MW solar βοΈ project in Bradford, FL (Florida Power & Light). Proposed completion changed from December 30, 2026 to January 16, 2031
Desoto County β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to April 29, 2033
Charlotte County β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to April 29, 2031
Charlotte County β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to April 29, 2031
Charlotte County β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to April 29, 2031
Charlotte County β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to April 29, 2031
Charlotte County β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from January 30, 2030 to October 30, 2031
Charlotte County β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from January 30, 2030 to October 30, 2031
Alva-Corbett 230kV β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Project status changed from Active In Queue to Operational
Quasar-Rice 230kV β 74MW solar βοΈ project in Putnam, FL (Florida Power & Light). Project status changed from Active In Queue to Operational
Keentown-Sunshine 230kV β 74MW solar βοΈ project in Manatee, FL (Florida Power & Light). Project status changed from Active In Queue to Operational
Duval-Raven 230kV β 74MW solar βοΈ project in Baker, FL (Florida Power & Light). Project status changed from Active In Queue to Operational
Alligator Swamp - North Brewton 230 kV line β 74MW solar βοΈ project in Escambia, FL (Florida Power & Light). Project status changed from Active In Queue to Operational
Eldora Sub β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Project status changed from Active In Queue to Operational
Eldora Sub β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Project status changed from Active In Queue to Operational
Collier County β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Project status changed from Active In Queue to Withdrawn
Hayfield Substation 230 kV β 74MW solar βοΈ project in Gilchrist, FL (Duke Energy Florida). Project status changed from Active In Queue to Suspended
Atwater Substation 115 kV β 74MW solar βοΈ project in Gadsden, FL (Duke Energy Florida). Project status changed from Active In Queue to Operational
Newberry Substation 230 kV β 74MW solar βοΈ project in Gilchrist, FL (Duke Energy Florida). Project status changed from Active In Queue to Operational
Radiant Switching Station 230 kV β 74MW solar βοΈ project in Columbia, FL (Duke Energy Florida). Project status changed from Active In Queue to Operational
Bradford-Columbia 115kV β 74MW solar βοΈ project in Union, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to July 30, 2028
Andytown-Orange River 500kV β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2026 to January 30, 2027
Alva-Corbett 230kV β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from July 30, 2026 to July 30, 2027
Sherman-Treasure 230kV β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to January 30, 2029
Heritage Solar-Malabar 230kV β 74MW solar βοΈ project in Brevard, FL (Florida Power & Light). Proposed completion changed from October 30, 2027 to July 30, 2028
Duval-Raven 230kV β 74MW solar βοΈ project in Baker, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to July 30, 2027
Shoal River - Pinckard (APC) 230kV line β 74MW solar βοΈ project in Walton, FL (Florida Power & Light). Proposed completion changed from July 30, 2026 to July 30, 2027
Sweatt-Nubbin β 74MW solar βοΈ project in Okeechobee, FL (Florida Power & Light). Proposed completion changed from July 30, 2026 to July 30, 2027
Eldora Sub β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from April 29, 2026 to January 30, 2027
Eldora Sub β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from April 29, 2026 to January 30, 2027
Eldora Sub β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from January 30, 2027 to July 30, 2028
Eldora Sub β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from January 30, 2027 to October 30, 2027
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from October 30, 2027 to July 30, 2028
Bermont Substation β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from July 30, 2026 to April 29, 2027
Bermont Substation β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from January 30, 2027 to January 30, 2029
Coachwhip-Sunshine β 74MW solar βοΈ project in Manatee, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to January 30, 2028
Raven - Sinai 161kV line β 74MW solar βοΈ project in Leon, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to July 30, 2028
Raven - Sinai 161kV line β 74MW solar βοΈ project in Leon, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to July 30, 2028
Raven - Sinai 161kV line β 74MW solar βοΈ project in Madison, FL (Florida Power & Light). Proposed completion changed from April 29, 2026 to April 29, 2027
Kiran-Eldora 230kV β 74MW solar βοΈ project in Indian River, FL (Florida Power & Light). Proposed completion changed from July 30, 2026 to April 29, 2027
Orange River-Whidden 230kV β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from July 30, 2026 to April 29, 2027
Kiran-Eldora 230kV β 74MW solar βοΈ project in Indian River, FL (Florida Power & Light). Proposed completion changed from January 30, 2027 to October 30, 2027
Coachwhip-Sunshine β 74MW solar βοΈ project in Manatee, FL (Florida Power & Light). Proposed completion changed from January 30, 2027 to July 30, 2029
Whidden Sub β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to October 30, 2027
South Bay-Alva β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2027 to July 30, 2028
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to January 30, 2028
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to January 30, 2028
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from April 29, 2026 to January 30, 2027
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from April 30, 2027 to January 30, 2029
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from July 30, 2028 to January 30, 2029
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from April 30, 2027 to January 30, 2031
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to July 30, 2031
Northern St. Lucie County β 74MW solar βοΈ project in Indian River, FL (Florida Power & Light). Proposed completion changed from July 30, 2028 to January 30, 2029
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from July 30, 2028 to January 30, 2031
Northern St. Lucie County β 74MW solar βοΈ project in Indian River, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to July 30, 2029
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to July 30, 2031
Northern St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from April 29, 2027 to January 30, 2031
Collier County β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Proposed completion changed from April 29, 2027 to January 30, 2028
Collier County β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to January 30, 2029
Whidden Sub β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from July 30, 2027 to January 30, 2029
Whidden Sub β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from July 30, 2027 to January 30, 2029
Whidden Sub β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to January 30, 2029
Whidden Sub β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from October 30, 2028 to April 29, 2031
Whidden Sub β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from October 30, 2028 to April 29, 2031
Whidden Sub β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from July 30, 2029 to April 29, 2031
SR70 Sweat-Whidden 230kV β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from October 30, 2028 to July 30, 2030
SR70 Sweat-Whidden 230kV β 74MW solar βοΈ project in Highlands, FL (Florida Power & Light). Proposed completion changed from April 29, 2027 to July 30, 2029
Southern St Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from January 30, 2027 to January 30, 2029
Southern Indian River County β 74MW solar βοΈ project in Indian River, FL (Florida Power & Light). Proposed completion changed from October 30, 2026 to January 30, 2028
Near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from July 30, 2027 to July 30, 2029
Near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from July 30, 2027 to July 30, 2029
Near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from July 30, 2027 to July 30, 2029
Near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to April 29, 2030
Near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to April 29, 2030
near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to April 29, 2030
Near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to April 29, 2030
Near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to October 30, 2030
near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to October 30, 2030
near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to October 30, 2030
near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from January 30, 2030 to October 30, 2030
near Indiantown β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from January 30, 2030 to October 30, 2030
Near Myakka City β 74MW solar βοΈ project in Manatee, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to January 30, 2030
Near Myakka City β 74MW solar βοΈ project in Manatee, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to January 30, 2030
Near Myakka City β 74MW solar βοΈ project in Manatee, FL (Florida Power & Light). Proposed completion changed from July 30, 2029 to July 30, 2033
Near Bermont β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from October 30, 2027 to January 30, 2030
Near Bermont β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from July 30, 2028 to January 30, 2030
Near Bermont β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to January 30, 2030
Near Bermont β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from October 30, 2027 to January 30, 2030
Near Bermont β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from July 30, 2028 to January 30, 2030
Near Bermont β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from July 30, 2028 to October 30, 2031
Near Bermont β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to October 30, 2031
Near Bermont β 74MW solar βοΈ project in Charlotte, FL (Florida Power & Light). Proposed completion changed from July 30, 2029 to October 30, 2031
Near LaBelle β 74MW solar βοΈ project in Desoto, FL (Florida Power & Light). Proposed completion changed from April 29, 2028 to January 30, 2030
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to July 30, 2029
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to July 30, 2029
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to July 30, 2029
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to July 30, 2029
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2028 to April 29, 2030
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2028 to April 29, 2030
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2028 to April 29, 2030
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2029 to April 29, 2030
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2029 to January 30, 2031
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2029 to January 30, 2031
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2029 to January 30, 2031
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2029 to July 30, 2031
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2029 to July 30, 2031
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2030 to July 30, 2031
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2030 to July 30, 2031
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2030 to January 30, 2032
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2030 to January 30, 2032
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2031 to January 30, 2032
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2030 to January 30, 2032
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2031 to April 29, 2032
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2031 to April 29, 2032
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2033 to October 30, 2032
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from October 30, 2033 to April 29, 2033
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2034 to April 29, 2033
Near LaBelle β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2034 to April 29, 2033
State Road 80 β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2032 to October 30, 2033
State Road 80 β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from June 29, 2032 to October 30, 2033
State Road 80 β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to July 30, 2030
State Road 80 β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2029 to July 30, 2030
State Road 80 β 74MW solar βοΈ project in Hendry, FL (Florida Power & Light). Proposed completion changed from January 30, 2030 to July 30, 2030
State Road 80 β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Proposed completion changed from December 30, 2029 to July 30, 2032
State Road 80 β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Proposed completion changed from December 30, 2029 to July 30, 2032
State Road 80 β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Proposed completion changed from December 30, 2030 to July 30, 2032
State Road 80 β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Proposed completion changed from December 30, 2030 to July 30, 2032
State Road 80 β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Proposed completion changed from December 30, 2031 to January 30, 2033
State Road 80 β 74MW solar βοΈ project in Collier, FL (Florida Power & Light). Proposed completion changed from December 30, 2031 to January 30, 2033
Martin Plant β 74MW solar βοΈ project in Martin, FL (Florida Power & Light). Proposed completion changed from January 30, 2028 to October 30, 2030
Indian River County β 74MW solar βοΈ project in Indian River, FL (Florida Power & Light). Proposed completion changed from January 30, 2030 to January 30, 2031
St. Lucie County β 74MW solar βοΈ project in St Lucie, FL (Florida Power & Light). Proposed completion changed from January 30, 2030 to July 30, 2029
Franklin 138 kV β 74MW battery + solar πβοΈ project in Greene County, PA (PJM). Project status changed from Active In Queue to Withdrawn
Blue Line Solar β 70MW solar βοΈ project in St Lawrence County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
NY48 - Diamond Solar β 60MW solar βοΈ project in Herkimer County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Mora Solar, Jack Frost-Lake Harmony 69 kV β 60MW solar βοΈ project in Carbon County, PA (PJM). Proposed completion changed from June 14, 2024 to December 30, 2027
Whale Square Energy Storage 1 β 58MW battery π project in Kings County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Sabinsville 115 kV β 50MW solar βοΈ project in Tioga County, PA (PJM). Project status changed from Active In Queue to Withdrawn
New Liberty - Boutwell 138 kV β 50MW battery + solar πβοΈ project in Hancock County, OH (PJM). Project status changed from Active In Queue to Withdrawn
Elkhorn City - Second Fork 69 kV β 50MW battery + solar πβοΈ project in Pike County, KY (PJM). Project status changed from Active In Queue to Withdrawn
Tierken Storage β 50MW battery π project in Rensselaer County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Adams 138 kV β 49MW battery + solar πβοΈ project in Adams County, OH (PJM). Project status changed from Active In Queue to Withdrawn
Victory Solar β 44MW solar βοΈ project in Crawford County, PA (PJM). Project status changed from Active In Queue to Withdrawn
Fort Myers Sub β 42MW gas π₯ project in Lee, FL (Florida Power & Light). Project status changed from Active In Queue to Operational
Mazon Blue - Lasalle 138 kV β 40MW solar βοΈ project in Grundy County, IL (PJM). Project status changed from Active In Queue to Withdrawn
NY128 - Foothills Solar β 40MW solar βοΈ project in Fulton County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
NY128 - Foothills Solar β 40MW solar βοΈ project in Fulton County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
New Jay PV & BESS β 39MW battery + solar πβοΈ project in Jay County, IN (PJM). Proposed completion changed from August 31, 2023 to September 16, 2027
Whitely 138 kV β 30MW battery + solar πβοΈ project in Greene County, PA (PJM). Project status changed from Active In Queue to Withdrawn
Holmes Creek - Defuniak Springs (PS) 115kV line β 24MW solar βοΈ project in Jackson, FL (Florida Power & Light). Proposed completion changed from July 30, 2027 to July 30, 2028
Bremo-Cartersville 230 kV II β 20MW battery π project in Cumberland County, VA (PJM). Project status changed from Active In Queue to Withdrawn
KCE NY 8a β 20MW battery π project in Greene County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Hampton Corners Solar β 20MW solar βοΈ project in Livingston County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Westtown II Energy Storage β 20MW battery π project in Orange County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Frosty Valley Energy Center, Columbia-Geisinger Tap #1 69 kV β 20MW solar βοΈ project in Columbia County, PA (PJM). Proposed completion changed from May 31, 2022 to January 14, 2027
Frosty Valley Energy Center, Columbia-Geisinger Tap #1 69 kV β 20MW solar βοΈ project in Anne Arundel County, MD (PJM). Proposed completion changed from May 31, 2022 to January 14, 2027
Niagara Solar β 20MW solar βοΈ project in Wyoming County, NY (NYISO). Proposed completion changed from May 31, 2025 to November 30, 2026
CS Hawthorn Solar β 20MW solar βοΈ project in Rensselaer County, NY (NYISO). Proposed completion changed from May 31, 2026 to November 30, 2026
Dolan Solar β 20MW solar βοΈ project in Washington County, NY (NYISO). Proposed completion changed from March 31, 2025 to November 30, 2026
Roosevelt Solar LLC β 19MW battery + solar πβοΈ project in St Lawrence County, NY (NYISO). Project status changed from Active In Queue to Withdrawn
Ritchie 69 kV β 17MW solar βοΈ project in Prince Georges County, MD (PJM). Project status changed from Active In Queue to Withdrawn